CPB Documentation Requirements

Jordan Millar Updated by Jordan Millar

Using the Table of Contents on the right, jump down to the section that explains the documentation requirements for the category of asset you wish to send to the project.

Ancillary Equipment

Document/Checklist

Method

Mandatory

Notes

Plant Risk Assessment

Machine Cab and ChekRite Portal

Yes

12 Months Maintenance/Service History

ChekRite Portal

Yes

Operators Manual

Machine Cab, Portal (optional)

Yes

Plant & Equipment Clean Down Declaration

ChekRite Mobile App

Yes

Plant Risk Assessment Review

ChekRite Mobile App

Yes

Asset Inspection Report

ChekRite Mobile App

Yes

Evidence of Vehicle Registration

ChekRite Portal

Conditional

Mandatory for road registered assets

OEM/Engineering approval for any attachments and/or modifications

ChekRite Portal

Conditional

Required where attachments / modifications are present

Annual Component Inspection - Rope / Hooks / Blocks etc

ChekRite Portal

Conditional

Mandatory for Cranes, hoists and Winches

Statutory Pressure Equipment Inspection as per AS3788

ChekRite Portal

Conditional

Mandatory where pressure equipment defined per AS 3788 is fitted

Other Relevant Documentation

ChekRite Portal

Conditional

Opportunity to upload other documents

Concrete Placing Equipment

Elevated Work Platform (EWP)

Heavy Vehicles (Road Vehicles Above 4.5 Tonne)

Light Vehicles (Road Vehicles up to 4.5 Tonne)

Mobile Cranes

Mobile Crusher & Screens

Mobile Plant

Piling & Drilling Rigs

Underground Equipment Specific

Document/Checklist

Method

Mandatory

Notes

Fire Suppression Service Sheet

ChekRite Portal

Conditional

Mandatory for equipment with installed power >125kW used in underground or tunneling works

Exhaust Gast Test Report

ChekRite Portal

Conditional

Mandatory for equipment used in underground or tunneling works

Hi-Rail Equipment Specific

Document/Checklist

Method

Mandatory

Notes

Rail Plant Registration

ChekRite Portal

Conditional

Mandatory for equipment configured for rail operations

Rail Authority Certificate

ChekRite Portal

Conditional

Mandatory for equipment configured for rail operations

Train Operating Conditions Waver

ChekRite Portal

Conditional

Mandatory for equipment configured for rail operations

Brake Test Report

ChekRite Portal

Conditional

Mandatory for equipment configured for rail operations

Rolling Stock Acceptance Form

ChekRite Portal

Conditional

Mandatory for equipment configured for light rail operations in NSW